Change Order Template

The change order template below is free to preview and install in Zealos. Manage change orders from request through approval with cascading impact analysis and a running CO log.

by Zealos

Pages in this template

  • 📋Change Order Request
  • 🔗Cascading Impact Analysis
  • 📊Change Order Log

Preview: Change Order Request

Change Order Request

💡

Complete this form for every proposed change to the original contract scope. Attach supporting documents (sketches, specs, photos) before routing for approval.

CO Details

Field

Value

CO Number

[CO-001]

Project Name

[Project Name]

Contract Number

[Contract #]

Date Initiated

[YYYY-MM-DD]

Requested By

[Name / Company]

Priority

[Standard / Urgent / Critical Path]


Parties

Role

Name

Company

Contact

Owner / Client

[Name]

[Company]

[Email / Phone]

General Contractor

[Name]

[Company]

[Email / Phone]

Architect of Record

[Name]

[Company]

[Email / Phone]

Subcontractor (if applicable)

[Name]

[Company]

[Email / Phone]


Description of Change

Reason for Change:

  • [Owner-directed change]

  • [Design error or omission]

  • [Unforeseen site condition]

  • [Code or regulatory requirement]

  • [Value engineering]

  • [Other: describe]

Detailed Description:

[Provide a detailed narrative of what is changing, why, and what areas of work are affected. Reference drawing numbers, spec sections, and RFI numbers as applicable.]

Reference Documents

  • [RFI #___]

  • [Drawing Sheet ___]

  • [Specification Section ___]

  • [Photo / Sketch attached]


Cost Impact

⚠️

All cost estimates must include labor, material, equipment, subcontractor markup, and overhead & profit per contract terms.

Item

Description

Qty

Unit

Unit Cost

Total

1

[Labor — trade description]

[X]

[hrs]

[$XX.XX]

[$X,XXX]

2

[Material — description]

[X]

[ea/lf/sf]

[$XX.XX]

[$X,XXX]

3

[Equipment rental]

[X]

[days]

[$XXX]

[$X,XXX]

4

[Subcontractor — name/trade]

[1]

[LS]

[$X,XXX]

[$X,XXX]

Subtotal

[$X,XXX]

Overhead & Profit (__ %)

[$XXX]

Total CO Value

[$X,XXX]

Net impact to contract value: [+ / - $X,XXX]


Schedule Impact

Field

Value

Days Added / Removed

[+/- X calendar days]

Affected Activities

[List critical path activities impacted]

Revised Substantial Completion

[YYYY-MM-DD]

Concurrent Work Possible?

[Yes / No — explain]


Approval Chain

Step

Role

Name

Date

Status

1

Submitted by (Requestor)

[Name]

[Date]

[Submitted]

2

Reviewed by (PM / Superintendent)

[Name]

[Date]

[Pending]

3

Approved by (GC Principal)

[Name]

[Date]

[Pending]

4

Approved by (Architect)

[Name]

[Date]

[Pending]

5

Approved by (Owner)

[Name]

[Date]

[Pending]


Verification Checklist

Scope clearly defined and not duplicated in other COs

Cost breakdown includes all labor, material, equipment, and markup

Schedule impact reviewed with superintendent

Downstream trade impacts identified (see Cascading Impact page)

Supporting documents attached (drawings, specs, photos)

Insurance and bonding implications reviewed if CO exceeds threshold

About this template

Change orders represent 20-30% of all construction project value — trillions of dollars transacting on one-page paper forms. This template digitizes the entire change order lifecycle: structured CO requests with cost and schedule impact, a cascading impact analysis that maps downstream effects across trades, and a running log to track cumulative scope creep. Built for general contractors, owners reps, and construction managers who need to control project cost and schedule.

Tags

change-orderAECcost-managementconstructionscope-change

Install this change order template in your workspace

Zealos is a personal operating system for revenue teams. Book a call and we'll set you up with this template.

Get started

More note templates